milestones
Bristol Airport interchange highly commended at Constructing Excellence national awards
Farrans says the Griffiths Farrans JV's public transport interchange at Bristol Airport was highly commended in Infrastructure Project of the Year, adding a national result to three regional wins earlier in 2026.
Farrans has said the Public Transport Interchange it delivered at Bristol Airport with joint venture partner Griffiths was highly commended in Infrastructure Project of the Year at the 2026 Constructing Excellence National Awards.
Constructing Excellence said the ceremony took place on Friday 6 November at the London Marriott Grosvenor Square Hotel; its own awards page, as read on 11 November, still listed finalists only and had not published results.
Farrans said its teams worked in partnership with Bristol Airport to deliver what it described as a modern, sustainable transport hub, and credited the recognition to its people, JV partners, supply chain and stakeholders. The announcement carried no named speaker.
Dave Lees, Chief Executive, Bristol Airport, said at handover in July 2025: "We're delighted to open the Public Transport Interchange ahead of schedule and on budget".
The finalist field
Constructing Excellence draws its national finalists from the winners of its regional awards programmes. It listed the Bristol Airport entry as "GriffithsFarrans JV and Bristol Airport", representing the South West, among eight regional winners in Infrastructure Project of the Year. The others included Canvey Island Southern Shoreline, Keel Crossing Sunderland, the M621 Junctions 1-7 scheme and Mumbles Coastal Protection Scheme.
The project was also a national finalist in Integration & Collaborative Working, alongside entries including Dyffryn Rhondda Tip Stabilisation and The Rob Burrow Centre for Motor Neurone Disease.
It reached the national stage after the Constructing Excellence South West Awards 2026, announced on 16 July at Aerospace Bristol, where Farrans said it had been shortlisted in five categories. CESW's winners page shows it took three: Infrastructure Project of the Year, Integration & Collaborative Working, and Health, Safety and Wellbeing. Farrans' project page also records a Transport Integration award at the 2026 NCE Airports Awards.
The project
Farrans puts the project value at £60m, within Bristol Airport's £400m transformation programme. The CESW winners page describes it as a £65m scheme bringing together the airport, the JV, designers and the supply chain.
Griffiths Farrans JV announced the contract award on 23 November 2023, when Bristol Airport said it was the largest single capital investment since the terminal opened in 2000 and would take 18 months to complete. The scheme comprised a public transport interchange and a multi-storey car park with more than 2,000 spaces.
Simon Dunn, Pre-Construction Director, Griffiths Farrans JV, said at the time: "This project is a great example of what can be achieved when both client and contractor work in an open and collaborative way".
Farrans said work began in May 2023 and the interchange was handed over ahead of programme on 22 July 2025. Award judges quoted on its project page described it as delivered two months ahead of schedule.
The interchange sits on top of the new car park, with level access to the terminal forecourt over a covered bridge link. Farrans said it has 16 bus and coach bays, up from five previously, and is expected to handle about 250 public transport movements a day. Its project page reports public transport mode share at the airport rising from about 15% to 19.5%.
| Bus and coach bays at Bristol Airport | Number |
|---|---|
| Before the interchange | 5 |
| New interchange | 16 |
Farrans said the site provided 120 jobs at peak and created more than 60 new jobs, more than 100,000 tonnes of stone and material were crushed and reused on site, and the project was used to trial the Volvo EC230 electric excavator.
Social value
On 2 December 2025 Farrans reported the project had delivered £14.1m of social return on investment, calculated using the TOMs framework, which it said represented 26% added value for the local community.
According to Farrans, the project supported 18 apprentices and two T-Level placements, more than 23% of staff came from within 20 miles of the airport, 30% of suppliers were based within a 50-mile radius, and £56,000 went to local community and charity initiatives.
Sources
- Farrans (opens in a new tab) (accessed 2026-11-11)
- Constructing Excellence (opens in a new tab) (accessed 2026-11-11)
- Constructing Excellence South West (opens in a new tab) (accessed 2026-11-11)
- Farrans (opens in a new tab) (accessed 2026-11-11)
- Farrans (opens in a new tab) (accessed 2026-11-11)
- Farrans (opens in a new tab) (accessed 2026-11-11)
- Farrans (opens in a new tab) (accessed 2026-11-11)
- Farrans (opens in a new tab) (accessed 2026-11-11)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.