Galliford Try wins £210m main construction contract for M5 junction 10 upgrade
Gloucestershire County Council has appointed Galliford Try to build the all-movements junction, link road and A4019 widening, with the existing slip roads expected to close for around two years from early 2027.

Galliford Try's Infrastructure business has won a £210m contract from Gloucestershire County Council to deliver the main construction works for the M5 Junction 10 Improvements Scheme near Cheltenham.
The council said the contract covers delivery of the full improvements, which will turn junction 10 into an all-movements junction so drivers can join and leave the M5 in all directions for the first time.
The works also include a new link road connecting the A4019 to the B4634 west of Cheltenham and widening of the A4019 Tewkesbury Road. The council said the scheme will provide new active travel facilities and flood mitigation measures.
Bill Hocking, Chief Executive for Galliford Try, said: "Our Infrastructure business remains a key part of our Sustainable Growth Strategy and the team has a strong track record in delivering schemes for the strategic road network."
The contractor's earlier role
Galliford Try has been working with the council on the scheme since June 2023, according to the council. Its original appointment followed a competitive tender to progress the scheme ahead of the Development Consent Order (DCO) application, working alongside the council's consultants Atkins, a member of the SNC-Lavalin Group.
Galliford Try's own announcement described that earlier work as the design phase. Hocking said the company looked forward to "continuing our collaboration with Gloucestershire County Council following the successful design phase".
Weather-dependent preparation works began on site in autumn 2025 and are being carried out by Galliford Try, the council said in January 2026. At that point the council said the main construction phase was due to start in autumn 2026.
Cllr Julian Tooke, Cabinet Member for Business, Economic Development, Planning and Infrastructure, said the award was "another significant milestone for the M5 Junction 10 Improvements Scheme".
Cost and funding
Both the council and Galliford Try put the overall scheme cost at £372m. Galliford Try said funding secured to date includes the UK Government's Housing Infrastructure Fund, administered by Homes England, through which the scheme was originally funded following the council's bid.
The council listed further sources including district council Community Infrastructure Levy funding and Section 106 contributions from developers whose sites will directly benefit from the scheme.
Galliford Try said the scheme is expected to enable more than 20,000 new homes, including over 7,000 affordable homes, and support around 12,000 skilled jobs. The council said it will support the Golden Valley development and the National Cyber Innovation Centre, and is intended to unlock the west and north-west Cheltenham developments.
The council is leading delivery in collaboration with National Highways and said the scheme builds on the £33m Arle Court Transport Hub.
Consent history
The council published its preferred route announcement on 16 June 2021 and ran a 10-week statutory consultation from 8 December 2021 to 15 February 2022.
It submitted the DCO application to the Planning Inspectorate on 19 December 2023, and the application was accepted for examination on 16 January 2024. After a six-month examination, the Examining Authority's recommendations went to the Secretary of State on 4 March 2025, and the Secretary of State for Transport granted development consent on 4 June 2025.
The Planning Inspectorate said it was the 58th transport application out of 157 applications it had examined at that date.
What happens next
The new junction layout adds a slip road onto the M5 southbound and a slip road off the M5 northbound. To build the most complex elements of the project, the council expects to close the existing northbound entry and southbound exit slip roads at junction 10 from early 2027.
The council said those closures are currently anticipated to remain in place for around two years, with signed diversion routes put in place and further details to be shared ahead of the closures.
On the record: Galliford Try, Homes England
Sources
- Galliford Try (opens in a new tab) (accessed 2026-11-26)
- Gloucestershire County Council (opens in a new tab) (accessed 2026-11-26)
- Gloucestershire County Council (opens in a new tab) (accessed 2026-11-26)
- Gloucestershire County Council (opens in a new tab) (accessed 2026-11-26)
- Planning Inspectorate (GOV.UK) (opens in a new tab) (accessed 2026-11-26)
- Gloucestershire County Council (opens in a new tab) (accessed 2026-11-26)
- Gloucestershire County Council (opens in a new tab) (accessed 2026-11-26)
This story was researched from the primary sources above and checked against them before publication. Spotted an error? Tell us and we will correct it promptly.